  • Construction of new 3,500sqft steel portal framed warehouse with first floor mezzanine area to meet client requirements specification in a design and build project.
  • First floor constructed using lightweight concrete on metal decking on compositely designed steel frame for economic reasons to limit steel depths.
  • Development primarily clad but with front corner in double storey height glazing.
  • Mass concrete pad and strip foundations adopted incorporating heave protection in highly shrinkable clay sub soil adjacent to trees.
  • Alterations to existing drainage and services network including pumped storm water drainage system connected to existing sewer.
  • New boundary wall constructed requiring close liaison with Party Wall Surveyors acting on behalf of numerous private residential properties to the rear of the site.
  • All works carried out whilst maintaining access to rear garage business.